Humber Gateway Offshore

Project Challenge

Subsea Energy Solutions were informed by EON of the imediate requirement for 200 off Snorkel Bungs for use as part of the Humber Gateway Offshore Windfarm project. The bungs were required to facilitate venting of monopolies during the grouting process.

The component requirements and associated challenges were as follows;

  1. Design bespoke Grout Snorkel Bungs and prove functionality of proposed product.
  2. Build and deliver initial prototype unit for initial pro-production testing.
  3. Refine and produce a further 200 units for production usage.
  4. End to end project delivery timescales to be completed within four weeks.
Project Solution

Upon receiving initial instructions, Subsea Energy Solutions had the initial prototype designed built and delivered within a two week timeframe.

Initial pre-production testing was completed and design refinements made as required.

Upon receipt of approval a two week project schedule remained for manufacture and delivery, within which all 200 units were manufactured, inspected and tested with all units completed and delivered within the project timeframe.

Project Outcome

All equipment and accompanying documentation were delivered to EON on the date required by client.

Subsea Energy Solutions understand all equipment was installed and successfully operated

The ultimate objective of the operation was to ensure venting whilst Grout filling.

Project was considered 100 % successful by all parties concerned.

 

 

 